Executive summary
Candent moved a semiconductor company’s integration from SAP PI/PO 7.2 to SAP Cloud Integration on SAP Integration Suite. More than 250 interfaces were migrated and more than 50 redesigned along the way, in five waves over eight months.
Business context and problem
The company’s integrations ran on SAP PI/PO 7.2 with manual monitoring and file- and RFC-based connectivity. SAP has named SAP Integration Suite as the successor to SAP Process Orchestration, and the company also wanted better performance from its integration layer.
Approach
- Every interface inventoried and assessed with SAP’s migration assessment tooling, then migrated as-is, redesigned or retired.
- Five waves, planned by interface complexity (simple, medium, complex) and frequency of use.
- A parallel run and a planned cut-over for each wave.
Before and after
| Dimension | Before | After |
|---|---|---|
| Platform | SAP PI/PO 7.2 | SAP Cloud Integration on SAP Integration Suite |
| Monitoring | Manual | Central monitoring and alerting in Integration Suite |
| Connectivity | File and RFC | SAP Cloud Connector for on-premise systems |
Solution architecture
| Layer | Detail |
|---|---|
| Integration platform | SAP Integration Suite – Cloud Integration |
| On-premise connectivity | SAP Cloud Connector |
| Connected systems | SAP S/4HANA, SAP SuccessFactors, third-party banking systems, CRM and third-party databases |
| Security | Certificates and OAuth, with keystore migration |
End-to-end flow
- Interface inventory exported from PI/PO and classified.
- Integration flows built or migrated in Cloud Integration; mappings tested.
- Parallel run against production-like data.
- Cut-over per wave; PI/PO channels switched off after sign-off.
Delivery
Eight months with a team of 15, in five migration waves.